Construction has started on several projects in the Central Eastside, Convention Center and Lloyd District areas. Click here for the latest look at expected traffic impacts.
Portland Streetcar Loop Project
East Burnside/Couch Couplet
Hawthorne/Madison Pavement Rehabilitation
Oak B Basin Sewer Project
MLK Viaduct Replacement
 |
Construction has begun on the Portland Streetcar Loop project. Currently, the contractor is relocating a water line that must be moved prior to installation of the streetcar tracks.
Approximately three blocks at a time will be under construction.
Work hours on Grand Avenue are typically 8:30 a.m. to 6:00 p.m. During work hours two lanes will be open to traffic. When work is not in progress there should be three lanes open through the work area.
Work has also begun on the East Burnside/Couch couplet project. Work is underway on SE Couch, and has affected traffic circulation. Local businesses are open and there is access to all businesses. Thank you for your patience during construction!
|
+++++++++++++++++++++++++++++++++++++++++++++++++++
Latest information supplied by the Portland Streetcar Loop project on expected traffic and parking impacts of the construction. http://www.portlandstreetcar.org/constupdates.php
This is a look ahead at expected traffic impacts from construction for next week for the Inner Eastside area.
This is a summary of expected traffic impacts from construction for the current week for the Inner Eastside area.
|
| |