|
|
|
|
Construction is almost 97% complete
The sewer tunnel is 22 feet in diameter and is six miles long. The tunnel route begins at SE 17th and McLoughlin Blvd. and ends on Swan Island where it is connected to the Confluent Shaft. The tunnel boring machine (TBM) started boring in May 2007 from the Opera Shaft and reached the Port Center Shaft at the Swan Island Pump Station in October 2009. The TBM reached its southern destination from the Opera Shaft to the McLoughlin Shaft in October 2010.
The Confluent Shaft (from the West Side Big Pipe) and the Port Center Shaft (from the East Side Big Pipe) connects to the Swan Island Pump Station. The pump station will pump sewage through the Portsmouth Force Main, a pressurized pipe Environmental Services is building as one of the East Side CSO projects. The force main will discharge to an existing tunnel, which will take the flow to the Columbia Boulevard Wastewater Treatment Plant.
Shafts Seven shafts were built along the alignment. The shafts connect existing overflow pipes to the East Side CSO Tunnel and provide aboveground access to the tunnel. The shafts are approximately 49 - 60 feet in diameter and 110 to 165 feet deep.
Project Schedule
¤ February 2003 Design Team Selected - Project Began
¤ July 2004 Preliminary Design - Completed
¤ February 2006 Final Design - Completed
¤ March 2006 Shaft Construction Began
¤ May 2007 Tunnel Excavation Began
¤ October 2009 North Drive Completed
¤ October 2010 South Drive Completed
December 2011 East Side Big Pipe Completed
|
|