April 2, 2008: UPDATE!! -- East Side Big Pipe -- UPDATE!!
WHERE IS ROSIE NOW?

Tunnel Update as of 05-04-08
-
The TBM has advanced 8254 LF to date.
-
Advanced 340 LF for the week.
-
Built 68 fiber rings this week.
-
Only 390 feet remain to get to Steel Bridge Shaft and 12,139 feet remain to get to Port Center Way.
-
Ring build continues to be good.
Environmental Services is working on final design of the Portsmouth Force Main...
Construction has begun on the shafts of the East Side CSO Tunnel Project.
What is a CSO?
|
|
|