Process & Timelines


Type I Procedure

This review procedure is required for some historic resource reviews that are small in scope or impact.

  • Pre-Application Conference - Optional unless it is a specific requirement of a review
  • Completeness - Staff notifies applicant of any missing information or materials within 14 days of submittal
  • Public Notice - Upon receipt of a complete application, public notice is mailed to all property owners within 100 feet and to the recognized organizations in which the site is located. At least 14 days are allowed for public comment.
  • Decision - Made administratively by staff within 21 days after the application is determined to be complete.
  • Appeal - To the State Land Use Board of Appeals (LUBA)

Type Ix Procedure

This review procedure is required for environmental resource enhancement, the simplest design reviews and the simplest land division preliminary plan reviews.

  • Pre-Application Conference - Optional unless it is a specific requirement of a review
  • Completeness - Staff notifies applicant of any missing information or materials within 21 days of submittal
  • Public Notice - Upon receipt of a complete application, public notice is mailed to all property owners within 100 feet and to the recognized organizations in which the site is located. At least 30 days are allowed for public comment.
  • Decision - Made administratively by staff within 45 days after the application is determined to be complete.
  • Appeal - To the State Land Use Board of Appeals (LUBA)

Type II Procedure

This review procedure is required for adjustments (similar to variances), most environmental reviews, some conditional uses and some design reviews.

  • Pre-Application Conference - Optional unless it is a specific requirement of a review
  • Completeness - Staff notifies applicant of any missing information or materials within 14 days of submittal
  • Public Notice - Upon receipt of a complete application, public notice is mailed to all property owners within 150 feet and to the recognized organizations within 400 feet of the site. At least 21 days are allowed for public comment
  • Decision - Made administratively by staff within 28 days after the application is determined to be complete
  • Appeal - To local hearing bodies such as the Adjustment Committee or the Hearings Officer, depending on the land use review

Type IIx Procedure

This review procedure is required for large land divisions or land divisions on sensitive lands or when 4 or more land use reviews are requested in one application.

  • Pre-Application Conference - Optional unless it is a specific requirement of a review
  • Completeness - Staff notifies applicant of any missing information or materials within 14 days of submittal
  • Public Notice - Upon receipt of a complete application, public notice is mailed to all property owners within 150 feet and to the recognized organizations in which the site is located. At least 14 days are allowed for public comment
  • Decision - Made administratively by staff within 42 days after the application is determined to be complete
  • Appeal - To local hearing bodies such as the Adjustment Committee or the Hearings Officer, depending on the land use review

Type III Procedure

This review procedure is required for more complex reviews such as some land divisions, conditional uses, zoning map amendments and comprehensive plan map amendments, environmental violations and design reviews.

  • Pre-Application Conference - Required prior to submittal of the land use review
  • Completeness - Staff notifies applicant of any missing information or materials within 21 days of submittal
  • Posting - The applicant must post the site at least 30 days before the hearing.
  • Public Notice - Upon receipt of a complete application, public notice is mailed to all property owners within 400 feet and to the recognized organizations within 1,000 feet of the site. The notice is mailed at least 20 days prior to the hearing.
  • Hearing - Occurs within 51 days after the application is determined to be complete. In cases of comprehensive plan map amendments and statewide planning goal exceptions, a second hearing is held before City Council.
  • Decision - Made by the review body following the public hearing
  • Appeal - To City Council. Appeal of a Type III decision made by the City Council is appealed to the State Land Use Board of Appeals (LUBA).

Type IV Procedure

This review procedure is required for demolition reviews.

  • Pre-Application Conference - Required prior to submittal of the land use review
  • Completeness - Staff notifies applicant of any missing information or materials within 21 days of submittal
  • Posting - The applicant must post the site at least 30 days before the hearing
  • Public Notice - Upon receipt of a complete application, public notice is mailed to all property owners within 400 feet and to the recognized organizations within 1,000 feet of the site. The notice is mailed at least 20 days prior to the hearing.
  • Public Meeting - Held before the Historic Landmarks Commission
  • Hearing - Occurs before City Council within 71 days after the application is determined to be complete
  • Decision - Made by City Council following the public hearing
  • Appeal - To the State Land Use Board of Appeals (LUBA)