PortlandOnline

POL Government Elected Officials Auditor Griffin-Valade Charter, Code & Policies City Code & Charter Online Code & Charter Title 5 Revenue and Finan Chapter 5.34 Public Improvements and Construction Services
5.34.890 Construction Manager/General Contractor (CM/GC).

(Amended by Ordinance Nos. 181547 and 185898, effective February 20, 2013.)

 

A.  General. The CM/GC form of contracting, as defined in Subsection  5.34.810 B., is a technically complex project delivery system.   Unlike the Design-Build form of contracting, the CM/GC form of contracting does not contemplate a "single point of responsibility" under which the Contractor is responsible for successful completion of all Work related to a performance Specification. The CM/GC has defined Contract obligations, including responsibilities as part of the project team along with the City and design professional, although in CM/GC there is a separate Contract between the City and design professional. In order to utilize the CM/GC method, the City must be able to reasonably anticipate the following types of benefits:

 

1.   Time Savings. The Public Improvement has significant schedule ramifications, such that concurrent design and construction are necessary in order to meet critical deadlines and shorten the overall duration of construction. The City may consider operational and financial data that show significant savings or increased opportunities for generating revenue as a result of early completion, as well as less disruption to public facilities as a result of shortened construction periods;

 

2.  Cost Savings. Early Contractor input during the design process is expected to contribute to significant cost savings. The City may consider value engineering, building systems analysis, Life Cycle Costing analysis and construction planning that lead to cost savings. The City shall specify any special factors influencing this analysis, including high rates of inflation, market uncertainty due to material and labor fluctuations or scarcities, and the need for specialized construction expertise due to technical challenges; and

 

3.  Technical Complexity. The Public Improvement presents significant technical complexities that are best addressed by a collaborative or team effort between the City, design professionals and Contractor, in which the Contractor will assist in addressing specific project challenges through pre-construction services. The City may consider the need for Contractor input on issues such as operations of the facility during construction, tenant occupancy, public safety, delivery of an early budget or GMP, financing, historic preservation, difficult remodeling projects and projects requiring complex phasing or highly coordinated scheduling.

 

B.  Authority. The City shall use the CM/GC form of contracting only in accordance with the requirements of these rules. See particularly, Section 5.34.820 on "Use of Alternative Contracting Methods".

 

C.  Selection. CM/GC selection criteria may include those factors set forth above in Subsection 5.34.840 B.2.

 

D.  Basis for Payment. The CM/GC process adds specified Construction Manager Personal Services to traditional General Contractor Work, requiring full Contract performance within a negotiated Guaranteed Maximum Price (GMP). The basis for payment is reimbursable direct costs as defined under the Contract, plus a fee constituting full payment for Work and Personal Services rendered, which together shall not exceed the GMP. See GMP definition at Subsection 5.34.810 G. and Pricing Mechanisms in Section 5.34.860.

 

E.  Contract Requirements. Contracting Agencies shall conform their CM/GC contracting practices to the following requirements:

 

1.   Setting the GMP. The GMP shall be set at an identified time consistent with industry practice, after supporting information reasonably considered necessary to its use has been developed, and the supporting information shall define with particularity both what is included and excluded from the GMP. A set of drawings and Specifications shall be produced establishing the GMP Scope.

 

2.  Adjustments to the GMP. The Contract shall clearly identify the standards or factors under which changes or additional Work will be considered outside of the Work Scope that warrants an increase in the GMP, as well as criteria for decreasing the GMP. The GMP shall not be increased without a concomitant increase to the Scope defined at the establishment of the GMP or most recent GMP amendment.

 

3.  Cost Savings. The Contract shall clearly identify the disposition of any cost savings resulting from completion of the Work below the GMP; that is, under what circumstances, if any, the CM/GC might share in those cost savings, or whether they accrue only to the City’s benefit. (Note that unless there is a clearly articulated reason for sharing such cost savings, they should accrue to the City .)

 

4.  Cost Reimbursement. The Contract shall clearly identify what items or categories of items are eligible for cost reimbursement within the GMP, including any category of "General Conditions" (a general grouping of direct costs that are not separately invoiced, subcontracted or included within either overhead or fee), and may also incorporate a mutually-agreeable cost-reimbursement standard.

 

5.  Audit. Cost reimbursements shall be made subject to final audit adjustment, and the Contract shall establish an audit process to ensure that Contract costs are allowable, properly allocated and reasonable.

 

6.  Fee. Compensation for the CM/GC's Personal Services and Work shall be paid on the basis of a fee that is inclusive of profit, overhead and all other indirect or non-reimbursable costs. Costs determined to be included within the fee should be expressly defined wherever possible. The fee, first expressed as a proposed percentage of all reimbursable costs, shall be identified during and become an element of the selection process. It shall subsequently be expressed as a fixed amount when the GMP is established.

 

7.  Incentives. The Contract shall clearly identify any economic incentives, the specific criteria that apply and their relationship to other financial elements of the Contract (including the GMP).

 

8.  Controlled Insurance Programs. For projects anticipated to exceed $75 Million, the Contract shall clearly identify whether an Owner Controlled or Contractor Controlled Insurance Program is anticipated or allowable. If so, the Contract shall clearly identify:

 

a.  anticipated cost savings from reduced premiums, claims reductions and other factors;

 

b.  the allocation of cost savings; and

 

c.  safety responsibilities and/or incentives.

 

9.  Early Work. The RFP shall clearly identify, whenever feasible, the circumstances under which any of the following activities may be authorized and undertaken for compensation prior to establishing the GMP:

 

a.  Early Procurement of materials and supplies;

 

b.  Early release of Bid packages for such things as site development; and

 

c.  Other advance Work related to critical components of the Contract.

 

10.  Subcontractor Selection. The Contract shall clearly describe the methods by which the CM/GC shall publicly receive, open and record Bids or price quotations, and competitively select Subcontractors to perform the Contract Work based upon price, as well as the mechanisms by which the City may waive those requirements. The documents shall also describe completely the methods by which the CM/GC and its affiliated or subsidiary entities may compete to perform the Work, including, at a minimum, advance notice to the public of the CM/GC's intent to compete and a public Opening of Bids or quotations by an independent party.

 

11.  Subcontractor Approvals and Protests. The Contract shall clearly establish whether the City must approve subcontract Awards, and to what extent, if any, the City will resolve Procurement protests of Subcontractors and suppliers. The related procedures and reporting mechanisms shall be established with certainty, including whether the CM/GC acts as the City’s representative in this process and whether the CM/GC's subcontracting records are considered to be public records. In any event, the City shall retain the right to monitor the subcontracting process in order to protect City’s interests.

 

12.  CM/GC Self-Performance. Whenever feasible, the Contract shall establish the elements of Work the CM/GC may self-perform without competition, including, for example, the Work of the job-site general conditions. In the alternative, the Contract shall include a process for City approval of CM/GC self-performance.

 

13.  Socio-Economic Programs. The Contract shall clearly identify conditions relating to any required socio-economic programs (such as Good Faith Efforts and Workforce Training and Hiring), including the manner in which such programs affect the CM/GC's subcontracting requirements, the enforcement mechanisms available, and the respective responsibilities of the CM/GC and City.


Title 5 Revenue and Finan
Chapter 5.01 (Repealed)
Chapter 5.04 Funds
Chapter 5.08 Payment Of Salaries, Wages And Expenses
Chapter 5.09 Deferred Compensation Plan
Chapter 5.10 City Charitable Campaign
Chapter 5.12 Assignment or Garnishment of Salaries, Wages or Claims
Chapter 5.16 Emergency Checks
Chapter 5.20 Budget Procedure
Chapter 5.24 Auditor's Records and Reports
Chapter 5.30 Collections and Foreclosure Process
Chapter 5.31 Collections & Foreclosure Process For Delinquent Sewer Safety Net Liens
Chapter 5.32 (Repealed)
Chapter 5.33 Goods and Services
Chapter 5.34 Public Improvements and Construction Services
Chapter 5.36 Property Control
Chapter 5.40 Demands and Disbursements
Chapter 5.44 (Repealed)
Chapter 5.48 Charges for Services Performed
Chapter 5.50 Collections Section
Chapter 5.52 Petty Cash and Checks
Chapter 5.56 Ambulance Service
Chapter 5.60 Miscellaneous Charges
Chapter 5.64 Miscellaneous Fiscal Provisions
Chapter 5.68 Professional, Technical and Expert Service Contracts
Chapter 5.72 Economic Development Projects
Chapter 5.73 Arts Education and Access Income Tax
Chapter 5.74 Acquisition of Public Art
Chapter 5.75 Claims Under ORS Chapter 195 and 197