A. Final reports. Upon completion of the rough grading work and that
final completion of the work the Director may require the following reports and
drawings and supplements thereto:
1. An as-graded grading plan prepared by the civil engineer
including original ground surface elevations, as-graded ground surface
elevations, lot drainage patterns, and locations and elevations of all surface
and sub-surface drainage facilities. He shall provide approval that the work
was done in accordance with the final approved grading plan.
2. A Soil Grading Report prepared by the soil engineer including
locations and elevations of field density tests, summaries of field and
laboratory tests and other substantiating data and comments on any changes
made during grading and their effect on the recommendations made in the soil
engineering investigation report. He shall provide approval as to the adequacy
of the site for the intended use.
3. A Geological Grading Report prepared by the engineering geologist
including a final description of the geology of the site including any new
information disclosed during the grading and the effect of same on
recommendations incorporated in the approved grading plan. He shall provide
approval as to the adequacy of the site for the intended use as affected by
geological factors.
B. Notification of completion. The permittee or his agent shall notify
the Director when the grading operation is ready for final inspection. Final
approval shall not be given until all work including installation of all
drainage facilities and their protective devices and all erosion control
measures have been completed in accordance with the final approved grading plan
and the required reports have been submitted.
|
| |