1. It is determined that approved erosion, sediment and pollutant control measures do not meet the purposes set forth in Subsection 10.30.020.A.
2. An alternate method, measure or control fails
to perform as claimed by the responsible party.
3. A change in project timing has occurred due
to an adverse change in weather.
4. During development, relevant new information
about soil, site, topography or water conditions is discovered.
5. Changes to the area or type of ground
disturbing activity or equipment used are proposed or implemented.
6. The project schedule has changed which
results in development being conducted at a different time of year than
originally accepted or approved.
7. Additional or substitute construction or maintenance materials or chemicals will be used during development that require pollutant BMPs as set out in the Erosion Control Manual.